Registration 1828

White Hill Pond Quarry                          

Proponent:   Cabot Ready Mix Limited

Summary of Environmental Assessment Process

Project Description:

The proponent proposes to construct and operate a 9.9 hectare quarry and a 700 metre access road adjacent to existing quarries that are located at the end of Granny Till Road, off Route 60, near Seal Cove.  The proposed quarry will be located within the municipal boundary of St. John’s.  The operation will consist of excavation and removal of sand and gravel deposits using excavators and loaders, with the material being trucked to the proponent’s concrete plant near the Manuels Bypass Road for crushing and washing.   Construction of the quarry is expected to begin in May 2016 and take three weeks to complete.    The quarry is expected to operate for approximately five years.

  • December 14, 2015 - The undertaking was registered.
  • January 22, 2016 - Deadline for public comments.
  • January 28, 2016 - The Minister's Decision is due.
  • February 11, 2016 - The Minister's Decision is due (extended).
  • March 1, 2016 - The Minister's Decision is due (extended).
  • March 17, 2016 - The Minister's Decision is due (extended).
  • April 7, 2016 - The Minister's Decision is due (extended).
  • May 12, 2016 - The Minister's Decision is due (extended).
  • June 7, 2016 - The Minister's Decision is due (extended).

  • Documents: Public Notices:

Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free opens new window

 
Last Updated:
This page and all contents are copyright, Government of Newfoundland and Labrador, all rights reserved.