Municipal Affairs and Environment

Registration 1711

Wabush 3 Open Pit Mine Project in Labrador West

Proponent: Iron Ore Company of Canada

Summary of Environmental Assessment Process

Project Description:

The proponent has submitted a proposal to construct and operate a new open pit mine at its Labrador West mine site. This will be a conventional open pit mine that will provide iron ore to IOC's existing concentrator plant and will also provide a new source of iron ore to extend the operating life of its Carol Project. The proposed footprint (464 hectares) is mostly greenfields and is located entirely within the Town of Labrador City Planning Boundary. Two ponds, Pumphouse Pond (7.5 hectares) and Drum Lake (5.6 hectares), will be removed or altered with the Project development. The proposed project will require a water extraction system, waste rock and overburden storage areas and a water treatment and discharge area - all to be located in order to avoid the Beverley Lake protected watershed.

  • May 23, 2013 - The undertaking was registered.
  • June 28, 2013 - Deadline for public comments.
  • July 5, 2013 - The minister’s decision is due.
  • July 24, 2013 - Environmental Impact Statement required.
  • August 27, 2013 - Environmental Assessment Committee Appointed.
  • October 3, 2013 - Draft Environmental Impact Statement Guidelines.
  • April 3, 2014 - Environmental Impact Statement Guidelines.
  • August 8, 2014 - Environmental Impact Statement Submitted for Review.
  • August 26, 2014 - Extension of EIS Review Period.
  • December 23, 2014 - EIS Amendment is Required.
  • March 3, 2015 - EIS Amendment Submitted for Review.
  • August 10, 2015 - EIS Amendment Accepted.
  • September 11, 2015 - The Minister announced that the project is released.