Project Description:

The project involves the construction of a rubble mound breakwater to provide protection to an adjacent finger pier wharf. The area between the breakwater and the existing finger pier wharf will also be infilled to provide an expanded service area. The breakwater will have an approximate length of 120 metres at the waters surface, extending in a generally southern direction with an overall footprint (breakwater and infill for new service area) of 7,000 square metres. The armourstone material will be trucked to the site and will be placed using an excavator(s), working above the high water mark, from the shoreline/breakwater structure or atop a barge. The successful contractor will determine the exact construction methodology and source for the armourstone. Construction is expected to require 3 to 4 months to complete and is tentatively scheduled for the 2010/2011 fiscal year.

  • May 14, 2010 - The undertaking was registered.
  • June 21, 2010 - Public comments are due.
  • June 28, 2010 - The Minister's decision is due.
  • July 7, 2010 - The project was released.

Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free opens new window

Last Updated:
This page and all contents are copyright, Government of Newfoundland and Labrador, all rights reserved.